Skip to main content
chargeport

EV charging time calculator — how long to charge your EV

Estimate end-to-end charging time for any vehicle on any station. Pick your battery size, current and target state of charge, and the station's kW rating (Level 1 / Level 2 / DCFC, or a custom number). The estimator applies the standard linear formula for AC charging and adds a realistic DC taper curve above 80% SoC, so a Supercharger or 350 kW DCFC stop comes out closer to what you'll actually see in the car.

Station / charger type

Estimated charging time

4 h 46 min

Energy delivered: 52.5 kWh · AC · 11 kW

AC linear: energy ÷ power. The car's onboard charger (OBC) is the real ceiling — if it's lower than the station kW, plug the OBC kW into the Custom field.

How the estimate is computed

  • AC charging (Level 1 / Level 2): linear — hours = energy needed (kWh) ÷ station power (kW). A 75 kWh battery going from 10% to 80% needs 52.5 kWh, which at 7.2 kW takes about 7 h 18 min.
  • DC fast charging: linear up to 80% SoC, then derated to roughly 30% of peak power between 80% and 100% — the standard model for lithium-ion taper. The 80–100% window typically adds 50–100% to the time of the 0–80% portion.
  • The actual bottleneck is whichever is smaller: the station's kW, the car's onboard charger ceiling on AC, or the car's DC peak. This estimator assumes the station rating IS the bottleneck; if your car can't accept the rated kW, plug your car's actual ceiling into the custom kW field.
  • Energy used = (target SoC − current SoC) ÷ 100 × battery kWh. No buffer is added for battery preconditioning losses (~3–8%); for road trips, mentally add 5%.

Worked examples

Common scenarios computed with the same model the calculator uses, so you can sanity-check the numbers against what you might see day to day.

Tesla Model Y (75 kWh) on a 250 kW Supercharger, 10 → 80%~ 21 min
Tesla Model Y (75 kWh) on a 250 kW Supercharger, 10 → 100%~ 51 min (taper)
Hyundai Ioniq 5 (77 kWh, 800 V) on 150 kW DCFC, 10 → 80%~ 22 min
Ford F-150 Lightning ER (131 kWh) on Level 2 11 kW, 10 → 100%~ 10 h 43 min
Chevy Bolt EV (66 kWh, 55 kW DC peak) on a 150 kW DCFC, 10 → 80%~ 50 min (Bolt's 55 kW ceiling is the bottleneck — set kW = 55)
Nissan Leaf (40 kWh) on Level 1 1.4 kW, 30 → 80%~ 14 h 18 min
Lucid Air (118 kWh, 19.2 kW OBC) on 19.2 kW Level 2, 20 → 100%~ 4 h 55 min

What this estimator does NOT model

  • Cold-weather derating — below freezing, DC fast-charge sessions can run 30–60% slower without preconditioning. See the cold-weather charging page.
  • Battery temperature curve — a session that starts on a hot battery (back-to-back stops on a road trip) can also taper earlier than 80%.
  • Per-vehicle DC curves — the Hyundai Ioniq 5 / Kia EV6 sustain near-peak longer than a Bolt EV; this estimator uses an industry-average curve.
  • Station load sharing — at a busy Supercharger or DCFC station, paired stalls can share a cabinet and deliver less than rated kW.
  • OBC ceiling for AC — most EVs cap at 7.2 or 11 kW even on a 19.2 kW Level 2 station. Adjust the kW field accordingly.

Related tools